ROAD CONSTRUCTION


Click here for current issue

 

Meeting Agendas
  Mayor
  Council Members
  Budget
City Manager
City Secretary’s office
  Municipal Court
  Code of Ordinance
Emergency Services
Public Works
Engineering
  Utility Forms
  Personnel
  Jobs
  
  JV Pool Calendar
JV Pool Rules
  Chamber of Commerce
Flood Control

           Recycle

 
Enter your email address to subscribe to the JV E-blast!

 


Some files contained in
 this website require
 Acrobat Reader.
Download it for free
Click here

 

 

 

Jersey Village
ROAD CONSTRUCTION

 

Current Road Construction Status

 Week of May 5th - May 9th:
  • New 12” water line will continue to be tied into lateral lines from Chichester to Leeds lane along with installation of new fire hydrants; testing of new 12” water line may occur on Friday.
  • Paving will continue up to Ashburton – weather permitting.
  • Driveways will be poured from Chichester to Mauna Loa – weather permitting.
  • Storm sewer tie ins should be completed along Argentina – weather permitting.

Street Bond Project General Information

Frequently Asked Questions

 

To get the latest updates on the Street Bond Project join our construction e-blast