Project Start Date:
Middle to end of March 2008
Project Length:
450 calendar days (contractor anticipates completing entire
project prior to
the
allotted
timeframe)
Construction Times:
Monday Friday 7:00 a.m. to 6:00 p.m.
Project
Description:
-
The
removal and new construction of existing concrete
roadways, driveways, and sidewalks.
-
The
removal and new construction of existing storm sewer
piping, manholes and inlets.
-
The
removal and new construction of existing water lines.
-
The
removal of existing street lights and replacement with
decorative street lights.
Street Bond Project Map
.gif)
(Click Image To Enlarge)
Streets Affected:
-
Argentina
Phase 1 & 2
-
Chichester
Phase 3
-
Glamorgan Phase 4
-
Leeds
Phase 5
-
Equador / Shanghai Phase 6 & 7 (will not be renovated
until school is out of session)
-
Carlsbad
/ Tahoe Phase 8 & 9
Notifications To Residents:
-
Street
Closures 1 to 2 weeks in advance of them actually
closing
-
Disruption of Water Services 48 to 72 hours in advance
of occurring normally 1 to 2 hours without water
-
Detours Routes posted with signage adjacent to
affected streets
*
The
official notice to proceed letter was issued to SER
Construction Partners, Ltd. on February 20, 2008 authorizing
the beginning of construction effective February 25, 2008.